A 42 MWp plant's provisional connection offer carried a reactive capability condition the originally specified inverters could not meet across the full voltage range. The issue surfaced three weeks before financial close.
Rebuilt the PowerFactory model from the actual equipment datasheets rather than the generic library models used in the original study
Identified the reactive shortfall at the low end of the voltage range and quantified it
Evaluated three remedies: inverter substitution, added STATCOM, and revised transformer tap range
Recommended the tap range change — the only option that did not move financial close
Presented the revised study to the network operator and closed the condition
A 7-storey 1970s office block had to stay occupied through a seismic retrofit. The original drawings were incomplete, concrete strength varied by 40% between cores, and the client could not vacate more than one floor at a time.

A die-cast aluminium pump housing was 22% over its mass target but the tool was already cut. A new tool would have cost the programme five months.

A sterile injectable facility's Grade B suite had to hold its pressure cascade through every airlock under GMP Annex 1, with the plant room footprint already fixed at 310 m² by the building design.